We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
We're experiencing intermittent issues with customers checking and reporting outages. We're sorry for any inconvenience & ask that you try again if you receive an error message the first time.
As of: 10:11 PM, 9/5/24Whether you need new electric or natural gas service, or are upgrading existing service, we will guide you through the process from beginning to end.
Phase 1, Initiation: Call Our Contact Center1:2 The Contact Center will issue you a Notification Number.
1:3 You will receive a return call within 1-3 days.
2:3 Discuss elevated pressure needs with us.
2:4 Discuss your site conditions with us.
2:5 Agree on an installation date with the Project Coordinator/Technician.
2:6 Set the date your site will be ready.
2:7 Be ready to have a detailed discussion about your natural gas or electric needs. This will help us determine the load you will place on our service, and what level of service to provide for you.
3:5 If further details are needed our Permitting Group will contact you.
3:6 Analyze, review and discuss your proposed service route with your Project Coordinator, based on current conditions and future needs.
3:7 We will send you a customer packet with a number of documents, including your cost estimate. The estimate will be provided on Form 97.
3:8 Discuss any issues with site preparation or coordination with your Project Coordinator.
3:9 Your Project Coordinator and other representatives will be available any time in the project to answer your questions.
Phase 4, Prerequisites: Get Legal Permission to Install and Maintain4:2 Do a final site walkthrough with a representative.
4:3 Discuss possible tree trimming with your Project Coordinator.
4:4 If needed, sign and return any contracts.
4:5 Get the legal documents you need for your installation. Your Project coordinator will help you determine what you need, and where to get them.
4:6 Share site coordination requirements (from your electrician, for example) with your Project Coordinator.
4:7 At this point we will send you your Go Ready form.
4:8 Provide us with documents that indicate the required inspections are complete.
4:9 Prepare your site within 3 inches of final grade.
4:10 If needed, have conduit installed per Consumers Energy requirements.